Orange Line Progresses at Pratu Nam Station with Earth Retaining Wall Construction
Matichon - Economy

Key summary
Construction of the Orange Line from Suan Chulalongkorn to Ya Rang Mueang is advancing, with civil works completed and system installation at 75.12%. The first train set arrived in Thailand in November, with all 16 sets expected by May 2027. Trial operations are scheduled for December 2027, followed by commercial service starting in January 2028. At Pratu Nam Station on Phetchaburi Road, progress stands at 41.85%, with diaphragm wall construction underway to prepare for excavation.